BOT Project of Tatay Hydropower Plant Officially Started Commercial Operation
2015-07-28  Source:  [Big] [Middle] [Small]

On 17th June, Tatay Hydropower Plant obtained Reply Letter from Electricity of Cambodia (EDC), which officially declared: from the date of 22nd June, 2015, Tatay Hydropower Plant officially enters the stage of commercial operation. 

 

Since 13th August last year when the 1# generator set finished commissioning and was successfully connected with the state grid, the past 10 months has witnessed the braveness, great endeavor to tackle tough, showed by Beijing Sanlian International Investment Corp. Ltd. and Tatay Hydropower Ltd. They worked together and achieved the continuous improvement for the hydropower station operation management, ensured it running smoothly, which provided strong support for the project into commercial operation.