CHMC Pakistan 500kV Electrical Power Transmission Line Project Accomplished the Acceptance
2019-01-02  Source:  [Big] [Middle] [Small]

On November 15, 2018, the 500kV Electrical Power Transmission Line Project (same tower double circuit quadripartion, from Thar to Matiari in Sindh Province, Pakistan) contracted and constructed by CHMC, got the Acceptance Certificate, which designated that the first EPC project contracted and constructed by CHMC in Pakistan , accomplished the acceptance. 


C:UsersDELLDesktop新闻稿件.中国重机巴基斯坦500kV输电线路项目顺利验收巴基斯坦500kV塔尔-马迪瑞同塔双回四分裂线路EPC项目.jpg

Picture 1. Pakistan 500kV Electrical Power Transmission Line EPC Project


This Project is an important section in Pakistan mainstay power grid. CHMC actively participated in the Project international bidding and won, signed the Project Contract on June 3, 2016. The electrification experiment for the whole line was passed at one-time on July 31, 2018. The accomplishment of this Project built a solid foundation for CHMC to further develop the Pakistan market and to bring about the “ Regional Rolling Development” Strategy.