Generator Equipment of CHMC Laos Nam Ngum 4 Hydropower Station, Entered Into the Manufacture Stage
2019-06-09  Source:  [Big] [Middle] [Small]

C:UsersDELLDesktop需翻译的新闻稿需翻译的新闻稿中国重机老挝南俄4水电站主机设备进入制造阶段8b1998c5f9d951de.jpg

Picture 1. The Coordination Meeting in Deyang

 

On April 11, 2019, the generator equipment coordination meeting of Laos Nam Ngum 4 Hydropower Station Project which was contracted and constructed by CHMC, was held in Deyang, Sichuan Province, China. The manufacture party, the installation party, and CHMC personnel concerned, attended the meeting.  

 

During the meeting, all parties deeply discussed and studied the generator equipment design and other work related. Combining the expected progress of mechanical-electrical installation and equipment manufacturing time, also based on the target node of the power generation for the first unit, all parties together analyzed the supply time of each batch of equipment, item by item, and reached an agreement on the issues related, determined the delivery time of each batch of equipment.

 

The successful coordination meeting, symbolized that the generator equipment of the Project had entered the manufacturing stage, and laid a foundation for the smooth realization of the construction goal of the Project.