Picture 1. 150t Load Test
Picture 2. 250t Load Test
Picture 3. Group Photo in Site
On February 15, 2021, The 200t bridge crane in the Main Plant of CHMC Laos Nam Ngum 4 Hydropower Station,completed the Load Test successfully.
CHMC Project Department and the construction units worked closely together, overcame the unfavorable factors such as the shortage of personnel caused by the epidemic situation, and ensured the successful completion of the load test of the bridge crane, obtained the “Opening Achievement” of the Project mechanical and electrical installation, which laid a solid foundation for the installation of subsequent major mechanical and electrical equipment such as buried parts, stator and rotor of hydro-wheel units.
It fully opened the installation of mechanical and electrical equipment in Laos Nam Ngum 4 Hydropower Station.