CHMC Was Rewarded “Outstanding Contribution Award “by EDC
2021-10-28  Source:  [Big] [Middle] [Small]

  


   

  

Picture 1. Certificate of Merit


  Recently CHMC was rewarded “Outstanding Contribution Award “by Electricité du Cambodge (EDC), to praise CHMC for its completion of Cambodia East Loop Net (PhaseΙ)Project with a high quality. The Project had completed the power transmission throughout the whole line. As an important part of Cambodia's State Grid, the Project would greatly alleviate the shortage of production and living electricity for local residents after being put into operation, and create favorable conditions for the rapid development of the regional economy.

   

  Cambodia East Loop Net (Phase Ι) Project officially began construction in March 2018. It included two new 50 MVA substations, one expansion station and the 275 km 230kV double-loop transmission lines, covering four provinces in the northeastern region of Cambodia.

   

  In the construction period, all staff of CHMC Project Department, prevented epidemic situation, fought against high temperature, united and overcame difficulties, carefully organized for the scientific construction, with high quality, high standards, successfully completed the construction task, in which the construction quality has been affirmed by the owners.